Vietnam's North–South high-speed railway: where it stands
Hanoi to Ho Chi Minh City in about 5.5 hours: where Vietnam's US$67 billion high-speed railway stands, how its targets have moved and what comes next.

- Status
- ApprovedFeasibility study and design
- Completion
- 2035Unchanged since Nov 2024. Government Resolution 106/NQ-CP (baochinhphu.vn)
- Construction start
- December 2027First stated
late 2027in Nov 2024. Government of Vietnam portal - Estimated cost
- About US$67.3 billionFirst stated
About US$67.6 billionin Nov 2024. Government of Vietnam portal
Where it stands
- The National Assembly approved the investment policy in November 2024.
- The project is in its feasibility study and design stage. In November 2026 a consortium led by SYSTRA of France was selected for the feasibility study and overall design, a 30-month contract.
Key facts
- Route
- Ngoc Hoi station (Hanoi) to Thu Thiem station (Ho Chi Minh City), through 15 provinces and cities Government of Vietnam portal
- Track
- New double track, standard gauge (1,435 mm), design speed 350 km/h National Assembly Resolution 172/2024/QH15 (Dai Bieu Nhan Dan)
- Stations
- 23 for passengers, 5 for freight National Assembly Resolution 172/2024/QH15 (Dai Bieu Nhan Dan)
- Hanoi to Ho Chi Minh City
- About 5.5 hours, against about 30 hours on the existing line AP, via ABC News
Timeline
A consortium led by SYSTRA (France), with Korea National Railway, Yooshin and Sambo (South Korea) and TEDI, TEDI South, TRICC and Hoang Long (Vietnam), is selected for the feasibility study and overall design. Approved price about VND10.2 trillion (about US$375 million) for 30 months; it was the only bidder. VnEconomy
The Ministry of Construction sets December 2027 as the start of construction. The target moved from before 31 December 2026. Government of Vietnam portal
Work starts on a separate line, the Hanoi to Quang Ninh high-speed railway built by VinSpeed, Vietnam's first inter-regional high-speed link. Government of Vietnam portal
The Prime Minister asks agencies to consider state, private and public-private investment models. VOV
Vingroup withdraws its registration to invest, to focus on other projects. Vietnam Investment Review
Earlier
VinSpeed, a Vingroup company, registers to invest in the project. The Investor
Government Resolution 106/NQ-CP sets the start of construction before 31 December 2026, earlier than the late 2027 first planned, and operation from 2035. Government Resolution 106/NQ-CP (baochinhphu.vn)
The National Assembly approves the investment policy (Resolution 172/2024/QH15): 1,541 km, 350 km/h, completion aimed at 2035. The first sections were planned to start in late 2027. National Assembly Resolution 172/2024/QH15 (Dai Bieu Nhan Dan)
What comes next
Contract negotiation between the project board and the consortium VnEconomy
Mid-term feasibility report fixing the route and the key stations, bridges and tunnelsWithin 12 months of the contract VnEconomy
Land boundary stakes handed to the provinces, within 3 months of the mid-term reportQ4 2027 VnEconomy
First construction at the terminal stations, Ngoc Hoi and Thu ThiemEnd of 2027 or early 2028 VnEconomy
What it changes
Hanoi to Ho Chi Minh City was the 4th busiest flight route in the world in 2025, with about 11 million seats scheduled, according to OAG. Without the railway, flying is the only fast way between the two cities. Officials have said the train is meant to complement air travel, not replace it.
It also brings the cities in between closer. Planning figures from 2024 put Hanoi to Vinh at 1 hour 18 minutes, Hanoi to Da Nang at 2 hours 42 minutes and Hanoi to Nha Trang at 4 hours 18 minutes.
For Overseas Vietnamese with family in more than one city, or choosing where to base themselves, that changes the map: Da Nang would sit under three hours by train from Hanoi.
More from Insights
All insights- Vietnam megaprojects: status, targets and timelinesThe big projects building Vietnam, from the North–South high-speed railway to Long Thanh airport and the metros. First and latest target dates, a source on every line, kept up to date.
- Venture capital in Vietnam, ten years inFrom $45 million in 2015 to $1.4 billion in 2021 and back to $509 million in 2025: ten years of venture capital in Vietnam, with Binh Tran of AVV.
- 10 years of venture capital in Vietnamwith Binh TranBinh Tran's mother did not celebrate when Klout sold. The news reached the press in 2014, and she called to ask if everything was okay and whether he still had a job. It closed six years of…