Ho Chi Minh City Ring Road 3 and Ring Road 4: where they stand
Two expressway rings around Ho Chi Minh City: Ring Road 3 (about 76 km) is in its final works, and Ring Road 4 (about 207 km) is under construction.

- Status
- Partly openRing Road 3 final works, Ring Road 4 building
- Ring Road 3 completion
- End of 2026First stated
30 June 2026in Aug 2022. Vietnam+ (VNA) - Ring Road 4 completion
- 2029Unchanged since Jun 2025. Tien Phong (HCMC Department of Construction)
- Estimated cost
- Ring Road 3: more than VND75,300 billionUnchanged since Nov 2026. Bao Van Hoa
Where it stands
- The first part of Ring Road 3 in use is the Nhon Trach bridge and about 8 km of road linking Dong Nai with Ho Chi Minh City, open to cars since 20 August 2025.
- In mid-November 2026 the 17 km elevated section in the former Thu Duc area was about 99% built but not yet open, with opening aimed at 30 November; the whole project stood at about 76%.
- Ring Road 4 is under construction: the former Binh Duong section started in June 2025, two Ho Chi Minh City sections broke ground on 29 August 2026, and Tay Ninh launched its two sections on 15 October 2026.
Key facts
- Ring Road 3 route
- About 76.3 km through Ho Chi Minh City (including the former Binh Duong province), Dong Nai and Tay Ninh (the former Long An province) Bao Van Hoa
- Ring Road 3 build
- Four expressway lanes in the first phase; widening to eight lanes is planned at a preliminary cost of about VND60,000 billion Bao Van Hoa
- Ring Road 4 route
- About 207 km through Ho Chi Minh City (including the former Binh Duong and Ba Ria-Vung Tau provinces), Dong Nai and Tay Ninh, of which about 48 km in the former Binh Duong area is a separate project; four lanes at up to 100 km/h first, eight lanes in the long-term plan Tuoi Tre
- Ring Road 4 funding
- About VND120,413 billion for 159 km in 10 component projects: about VND69,800 billion from central and local budgets, the rest from investors under PPP Dai Bieu Nhan Dan (National Assembly resolution text)
- Ring Road 4, former Binh Duong section
- Approved and built as a separate project, under construction since 18 June 2025 with completion expected in 2027 Tien Phong
- Who leads
- The Ho Chi Minh City People's Committee is the main implementer of Ring Road 3 Government News (VGP)
Timeline
The 17 km elevated section of Ring Road 3 is about 99% built and aims to open on 30 November 2026. The Binh Chuan to Binh Goi road package sets 30 March 2027 as its target. Vietnam+ (VNA)
Tay Ninh launched Ring Road 4 component projects 2-4 and 2-5, from Thay Cai canal to Hiep Phuoc port, under PPP. The Tay Ninh section is nearly 78 km, worth over VND43,000 billion. VOV
Ho Chi Minh City broke ground on two Ring Road 4 expressway sections: Toc Tien-Chau Pha to Chau Duc bridge (about US$200 million) and Saigon River to Thay Cai canal (about US$334 million). VietNamNet
Ring Road 3 target moved from 30 June 2026 to the end of 2026: about 38.6 km of main line by 30 September and the full 70.4 km main line by 30 December. The city cited material shortages and higher input costs. Bao Lam Dong
Technical opening of the 14.7 km Ring Road 3 section through the former Thu Duc City, including Kenh Thay Thuoc bridge. A technical opening comes before regular service. Bao Dau Tu
Earlier
The Nhon Trach bridge and about 8 km of Ring Road 3 between Dong Nai and the Ho Chi Minh City - Long Thanh - Dau Giay expressway opened. Cars could use it from 20 August; trucks over 1.5 tonnes and coaches with 16 or more seats were not yet allowed. VTC News
The National Assembly approved Ring Road 4 at about VND120,413 billion for 159 km, with operation set for 2029. Dai Bieu Nhan Dan (National Assembly resolution text)
Construction began on the Ring Road 4 section through Binh Duong province (now part of Ho Chi Minh City), expected to be completed in 2027. Tien Phong
Prime Minister Pham Minh Chinh attended the groundbreaking of Ring Road 3 in Ho Chi Minh City. Government News (VGP)
The Government set 30 June 2026 as the completion date for Ring Road 3, with construction to start in June 2023. Government News (VGP)
The National Assembly approved the 76.34 km Ring Road 3 at about VND75,370 billion, to be largely built in 2025 and in use from 2026. Government News (VGP)
What comes next
Open the 17 km elevated section of Ring Road 3 from the interchange with the Ho Chi Minh City - Long Thanh - Dau Giay expressway to Tan Van; shortages of asphalt and stone could affect the date30 November 2026 Vietnam+ (VNA)
Finish the Ring Road 3 main line of about 70.4 km and about 75 km of parallel and access roads30 December 2026 Bao Lam Dong
Finish the 8.9 km Binh Chuan to Binh Goi section of Ring Road 3; the traffic systems, operations building and weighing stations follow in early 202730 March 2027 for the road package Vietnam+ (VNA)
Build the 46 km Ring Road 4 expressway section through Dong Nai, about VND16,270 billion2029 Tien Phong
What it changes
Ring Road 3 gives traffic between Dong Nai, the former Binh Duong area and the western districts a way around Ho Chi Minh City instead of through it. The Nhon Trach bridge already adds a direct link between the city and Dong Nai, and the elevated section is meant to open in step with Long Thanh International Airport.
Ring Road 4 runs further out, about 207 km through Ho Chi Minh City, Dong Nai and Tay Ninh. The city says it should ease traffic between provinces and shorten trips between industrial centres, seaports and international airports.
For Overseas Vietnamese who fly home or move to the south, the two rings mainly change trips that skip the city centre, such as from Long Thanh airport or Dong Nai to the former Binh Duong area or the Mekong Delta, once the remaining sections open.
More from Insights
All insights- Vietnam megaprojects: status, targets and timelinesThe big projects building Vietnam, from the North–South high-speed railway to Long Thanh airport and the metros. First and latest target dates, a source on every line, kept up to date.
- Venture capital in Vietnam, ten years inFrom $45 million in 2015 to $1.4 billion in 2021 and back to $509 million in 2025: ten years of venture capital in Vietnam, with Binh Tran of AVV.
- 10 years of venture capital in Vietnamwith Binh TranBinh Tran's mother did not celebrate when Klout sold. The news reached the press in 2014, and she called to ask if everything was okay and whether he still had a job. It closed six years of…