Two expressway rings around Ho Chi Minh City: Ring Road 3 (about 76 km) is in its final works, and Ring Road 4 (about 207 km) is under construction.

An elevated road over a canal in Ho Chi Minh City
Status
Partly openRing Road 3 final works, Ring Road 4 building
Ring Road 3 completion
End of 2026First stated 30 June 2026 in Aug 2022. Vietnam+ (VNA)
Ring Road 4 completion
2029Unchanged since Jun 2025. Tien Phong (HCMC Department of Construction)
Estimated cost
Ring Road 3: more than VND75,300 billionUnchanged since Nov 2026. Bao Van Hoa

Where it stands

Key facts

Ring Road 3 route
About 76.3 km through Ho Chi Minh City (including the former Binh Duong province), Dong Nai and Tay Ninh (the former Long An province) Bao Van Hoa
Ring Road 3 build
Four expressway lanes in the first phase; widening to eight lanes is planned at a preliminary cost of about VND60,000 billion Bao Van Hoa
Ring Road 4 route
About 207 km through Ho Chi Minh City (including the former Binh Duong and Ba Ria-Vung Tau provinces), Dong Nai and Tay Ninh, of which about 48 km in the former Binh Duong area is a separate project; four lanes at up to 100 km/h first, eight lanes in the long-term plan Tuoi Tre
Ring Road 4 funding
About VND120,413 billion for 159 km in 10 component projects: about VND69,800 billion from central and local budgets, the rest from investors under PPP Dai Bieu Nhan Dan (National Assembly resolution text)
Ring Road 4, former Binh Duong section
Approved and built as a separate project, under construction since 18 June 2025 with completion expected in 2027 Tien Phong
Who leads
The Ho Chi Minh City People's Committee is the main implementer of Ring Road 3 Government News (VGP)

Timeline

  1. The 17 km elevated section of Ring Road 3 is about 99% built and aims to open on 30 November 2026. The Binh Chuan to Binh Goi road package sets 30 March 2027 as its target. Vietnam+ (VNA)

  2. Tay Ninh launched Ring Road 4 component projects 2-4 and 2-5, from Thay Cai canal to Hiep Phuoc port, under PPP. The Tay Ninh section is nearly 78 km, worth over VND43,000 billion. VOV

  3. Ho Chi Minh City broke ground on two Ring Road 4 expressway sections: Toc Tien-Chau Pha to Chau Duc bridge (about US$200 million) and Saigon River to Thay Cai canal (about US$334 million). VietNamNet

  4. Ring Road 3 target moved from 30 June 2026 to the end of 2026: about 38.6 km of main line by 30 September and the full 70.4 km main line by 30 December. The city cited material shortages and higher input costs. Bao Lam Dong

  5. Technical opening of the 14.7 km Ring Road 3 section through the former Thu Duc City, including Kenh Thay Thuoc bridge. A technical opening comes before regular service. Bao Dau Tu

Earlier
  1. The Nhon Trach bridge and about 8 km of Ring Road 3 between Dong Nai and the Ho Chi Minh City - Long Thanh - Dau Giay expressway opened. Cars could use it from 20 August; trucks over 1.5 tonnes and coaches with 16 or more seats were not yet allowed. VTC News

  2. The National Assembly approved Ring Road 4 at about VND120,413 billion for 159 km, with operation set for 2029. Dai Bieu Nhan Dan (National Assembly resolution text)

  3. Construction began on the Ring Road 4 section through Binh Duong province (now part of Ho Chi Minh City), expected to be completed in 2027. Tien Phong

  4. Prime Minister Pham Minh Chinh attended the groundbreaking of Ring Road 3 in Ho Chi Minh City. Government News (VGP)

  5. The Government set 30 June 2026 as the completion date for Ring Road 3, with construction to start in June 2023. Government News (VGP)

  6. The National Assembly approved the 76.34 km Ring Road 3 at about VND75,370 billion, to be largely built in 2025 and in use from 2026. Government News (VGP)

What comes next

  1. Open the 17 km elevated section of Ring Road 3 from the interchange with the Ho Chi Minh City - Long Thanh - Dau Giay expressway to Tan Van; shortages of asphalt and stone could affect the date30 November 2026 Vietnam+ (VNA)

  2. Finish the Ring Road 3 main line of about 70.4 km and about 75 km of parallel and access roads30 December 2026 Bao Lam Dong

  3. Finish the 8.9 km Binh Chuan to Binh Goi section of Ring Road 3; the traffic systems, operations building and weighing stations follow in early 202730 March 2027 for the road package Vietnam+ (VNA)

  4. Build the 46 km Ring Road 4 expressway section through Dong Nai, about VND16,270 billion2029 Tien Phong

See every project on the Vietnam megaprojects map

What it changes

Ring Road 3 gives traffic between Dong Nai, the former Binh Duong area and the western districts a way around Ho Chi Minh City instead of through it. The Nhon Trach bridge already adds a direct link between the city and Dong Nai, and the elevated section is meant to open in step with Long Thanh International Airport.

Ring Road 4 runs further out, about 207 km through Ho Chi Minh City, Dong Nai and Tay Ninh. The city says it should ease traffic between provinces and shorten trips between industrial centres, seaports and international airports.

For Overseas Vietnamese who fly home or move to the south, the two rings mainly change trips that skip the city centre, such as from Long Thanh airport or Dong Nai to the former Binh Duong area or the Mekong Delta, once the remaining sections open.

What does Overseas Vietnamese mean?

Get updates when this changes.

Changes to this page go out in the OV Vietnam Brief, with Vietnam’s big stories explained.

One click to unsubscribe, in every email. Privacy Policy.

Become a member.

OV is the global network of Vietnamese professionals, 1,000 members in 50+ cities. Members get full access to everything OV runs and the right introductions when they need them.

Apply to join