Ho Chi Minh City and Hanoi metros: where they stand
Three metro lines run in Ho Chi Minh City and Hanoi, more are under construction, and both cities plan hundreds of kilometres of metro by 2035.

- Status
- Partly openThree lines open, more being built
- HCMC Line 2 opening
- Q4 2030First stated
2018in Jan 2010. VnEconomy - Hanoi Line 3 full opening
- December 2027First stated
2015in Sept 2010. Hanoi People's Committee portal - HCMC Line 1 opening
- Opened 22 December 2024First stated
2018in Jan 2012. The Investor
Where it stands
- Three metro lines run: HCMC Line 1 since December 2024, and in Hanoi, Line 2A since 2021 and the elevated part of Line 3 since August 2024.
- Hanoi Line 3's underground part was 79.3% built in May 2026, and HCMC Line 2 moved from preparation to full construction in July 2026.
- Both cities build under Resolution 188, which the National Assembly passed in February 2025: Ho Chi Minh City plans 355 km of metro by 2035 and Hanoi about 500 km.
Key facts
- HCMC Line 1
- Ben Thanh to Suoi Tien, nearly 20 km with 3 underground and 11 elevated stations, about 29 minutes end to end The Investor
- HCMC Line 1 first year
- Nearly 19 million passengers from 22 December 2024 to 15 December 2025, about 52,000 a day VietNamNet
- HCMC Line 2
- Ben Thanh to Tham Luong, about 11.3 km with 10 underground stations and 1 elevated; about VND55.2 trillion (US$2.1 billion) from the city budget VnEconomy
- Hanoi Line 2A
- Cat Linh to Ha Dong, 13.1 km, fully elevated, in commercial operation since 6 November 2021 Hanoi People's Committee portal
- Hanoi Line 3
- Nhon to Hanoi Railway Station, 12.5 km with 8 elevated and 4 underground stations; the 8.5 km elevated part to Cau Giay runs since 8 August 2024 Hanoi People's Committee portal
- Hanoi riders
- Over 62.2 million passengers on Lines 2A and 3 by 30 April 2026 Hanoi People's Committee portal
Timeline
Ho Chi Minh City asks Line 2 contractors to aim for completion in 2029, a year ahead of the 2030 schedule. Dan Tri International (DTiNews)
Ho Chi Minh City: work starts on the first major part of Line 2, the diaphragm wall of Pham Van Bach station, a launch site for the tunnel boring machines. Viet Nam News
Hanoi breaks ground on five metro lines totalling 298.5 km, including Line 1 and Line 2 to Noi Bai International Airport. Government portal (baochinhphu.vn)
Hanoi: the Line 3 underground part reaches 79.3%, with both tunnels bored; the city sets December 2027 as the target for its commercial operation. Hanoi People's Committee portal
Ho Chi Minh City breaks ground on Line 2 (Ben Thanh–Tham Luong), the first project under Resolution 188, with completion set for the fourth quarter of 2030. VnEconomy
Earlier
Hanoi breaks ground on the Nam Thang Long–Tran Hung Dao section of Line 2, worth about VND35.7 trillion (US$1.4 billion). Tuoi Tre News
The National Assembly passes Resolution 188, giving Hanoi and Ho Chi Minh City special powers on funding, preparation and contractor choice for urban rail. VTV
Ho Chi Minh City: Line 1 (Ben Thanh–Suoi Tien) opens for commercial service, 12 years after construction began. The Investor
Hanoi: the 8.5 km elevated part of Line 3, from Nhon to Cau Giay, opens for commercial service. Hanoi People's Committee portal
Hanoi: Line 2A (Cat Linh–Ha Dong) opens as Vietnam's first metro line. Its first target, set on approval in 2008, was 2013. VnExpress International
What comes next
Hanoi Line 3: systems and equipment installed in the four underground stations, then testing, trial runs and commercial operation of the underground partInstallation April 2027, operation December 2027 Hanoi People's Committee portal
HCMC Line 2: two tunnel boring machines start from Pham Van Bach and Le Thi Rieng stations; the city aims to move the start up two months from October 2027August 2027 Dan Tri International (DTiNews)
Hanoi Line 2: the first section, Nam Thang Long to Tran Hung Dao, under construction since 9 October 2025 at a cost of about VND35.7 trillion, is scheduled to begin commercial operation2029 Tuoi Tre News
Hanoi: five new lines (1, 2, 8, 10 and 14), started on 22 June 2026, to be substantially complete2030 VTV
What it changes
In Ho Chi Minh City, Line 1 runs from Ben Thanh to Suoi Tien in about 29 minutes and served nearly 19 million passengers in its first year. Line 2 will link Ben Thanh with the northwest of the city and meet Line 1 at Ben Thanh station, which is planned as the hub of the whole network.
In Hanoi, Lines 2A and 3 had served over 62.2 million passengers by April 2026. Once its four underground stations open, Line 3 will run its full 12.5 km from Nhon to Hanoi Railway Station. Line 2 will later connect the city centre with Noi Bai International Airport.
For Overseas Vietnamese who travel home or move to Vietnam, both cities have metro lines from the centre to fast-growing districts, Thu Duc in Ho Chi Minh City and Ha Dong and Cau Giay in Hanoi, with more lines due by 2030.
Cover photo: HikariTenshi, Wikimedia Commons, CC BY 4.0.
More from Insights
All insights- Vietnam megaprojects: status, targets and timelinesThe big projects building Vietnam, from the North–South high-speed railway to Long Thanh airport and the metros. First and latest target dates, a source on every line, kept up to date.
- Venture capital in Vietnam, ten years inFrom $45 million in 2015 to $1.4 billion in 2021 and back to $509 million in 2025: ten years of venture capital in Vietnam, with Binh Tran of AVV.
- 10 years of venture capital in Vietnamwith Binh TranBinh Tran's mother did not celebrate when Klout sold. The news reached the press in 2014, and she called to ask if everything was okay and whether he still had a job. It closed six years of…