North–South expressway: where it stands
Vietnam's eastern North–South expressway runs about 2,063 km from the China border in Lang Son to Ca Mau. Chi Lang to Ca Mau is open; the border section is finishing.

- Status
- Partly openChi Lang to Ca Mau open; border section finishing
- Full route open
- 2026First stated
2025in Nov 2024. Bao Dau Thau (Government Office notice 506/TB-VPCP) - 12 central sections in service
- April 2026First stated
2025in Jan 2022. Ha Tinh provincial portal (VOV, Ministry of Construction) - Estimated cost
- VND146,990 billion for the 729 km 2021 to 2025 phaseUnchanged since Jan 2022. Bao Van Hoa
Where it stands
- The expressway runs from Chi Lang in Lang Son all the way to Ca Mau. The last sections of the 2021 to 2025 phase, in the central provinces, opened their main lines in May 2026.
- The final 60 km, from Chi Lang to the Huu Nghi border gate, is still being finished. Its first 27 km were technically opened in May 2026, and the government wants the whole section done in 2026.
- The next stage is widening. The Ministry of Construction has proposed two PPP projects to take 966 km of four-lane road to six lanes.
Key facts
- Route
- About 2,063 km, from Huu Nghi border gate in Lang Son to Ca Mau Dtinews (chinhphu.vn)
- 2017 to 2020 phase
- About 654 km in three segments, preliminary cost VND118.7 trillion (about US$5.22 billion), approved by the National Assembly on 22 November 2017 VietNamNet
- 2021 to 2025 phase
- About 729 km in 12 sections, public investment, from Bai Vot to Cam Lo, Quang Ngai to Nha Trang and Can Tho to Ca Mau VnEconomy
- Size
- Four lanes on a 17 m roadbed in the first stage, to be widened to 24.75 m later; a maximum of 80 km/h on the Can Tho to Ca Mau section Dtinews
- Border section
- Huu Nghi to Chi Lang is a BOT project under a contract with the Lang Son People's Committee; construction began on 21 April 2024 CafeF
- Tolls
- 10 state-funded sections were tolled by July 2026, collecting VND1,620 billion by 21 July 2026 CafeF (Bao Chinh phu)
Timeline
The Ministry of Construction proposed two PPP projects to widen 966 km to six lanes: Mai Son to Cam Lo (415 km) and Quang Ngai to Dau Giay (551 km), at a preliminary VND150.4 trillion. VietNamNet
The Permanent Deputy Prime Minister asked for the Huu Nghi to Chi Lang border section to be finished in 2026, and for a study on opening it free of charge for Tet 2027. Bao Dau Thau
Tolls on the five Quang Ngai to Nha Trang sections were set to start on 14 August 2026, after the Bai Vot to Cam Lo sections began tolling on 15 July. CafeF (Bao Chinh phu)
The first 27 km of the Huu Nghi to Chi Lang border section were technically opened, linking the Bac Giang to Lang Son expressway with Lang Son city. Dai Bieu Nhan Dan
The main line of the 48 km Chi Thanh to Van Phong section went into service on 18 May; some local roads, one tunnel tube and traffic systems were still being finished in June. Nguoi Quan Sat
Earlier
The Quy Nhon to Chi Thanh section opened over its full length of nearly 62 km. VOH
About 178 km opened in Quang Ngai and Gia Lai: the 88 km Quang Ngai to Hoai Nhon section, the 70.1 km Hoai Nhon to Quy Nhon section and over 20 km of Quy Nhon to Chi Thanh. SGGP
The full 110 km Can Tho to Ca Mau section opened, bringing the expressway to Ca Mau. VnEconomy
Four central sections, Quang Ngai to Hoai Nhon, Hoai Nhon to Quy Nhon, Quy Nhon to Chi Thanh and Chi Thanh to Van Phong, were technically opened. A technical opening comes before regular service. Nhan Dan
The Prime Minister asked for the expressway from Cao Bang to Ca Mau to be completed by the end of 2025. VietnamPlus (VNA)
The National Assembly approved the 729 km second phase in 12 sections, at VND146,990 billion, to be basically complete in 2025. VnEconomy
What comes next
Finish the 60 km Huu Nghi to Chi Lang border section, and study a proposal to open it free of charge for the Tet holiday2026, Tet 2027 for temporary use Bao Dau Thau
Hand over the remaining land at Huu Nghi to Chi Lang interchanges and frontage roads; the contract sets completion in December 2026December 2026 CafeF
Widen 966 km to six lanes in two PPP projects, Mai Son to Cam Lo and Quang Ngai to Dau Giay, at a preliminary VND150.4 trillion VietNamNet
Reach more than 5,000 km of expressways nationwide2030 Government Office notice 422/TB-VPCP
What it changes
The Can Tho to Ca Mau section brought the trip between the two cities down to about an hour and a half. In the far north, the first 27 km at Lang Son cut the drive from the end of the Bac Giang to Lang Son expressway to Ky Lua from about 40 minutes to about 17.
Vietnam had 1,163 km of expressways in 2020 and 3,345 km of main routes by the end of 2025. Most sections have four lanes on a 17 m roadbed for now, and the government plans to widen them to six lanes and reach more than 5,000 km nationwide by 2030.
For Overseas Vietnamese who fly into Hanoi or Ho Chi Minh City and visit family in the provinces, one expressway runs from Lang Son past Hanoi, Hue and Da Nang to Ho Chi Minh City, Can Tho and Ca Mau.
More from Insights
All insights- Vietnam megaprojects: status, targets and timelinesThe big projects building Vietnam, from the North–South high-speed railway to Long Thanh airport and the metros. First and latest target dates, a source on every line, kept up to date.
- Venture capital in Vietnam, ten years inFrom $45 million in 2015 to $1.4 billion in 2021 and back to $509 million in 2025: ten years of venture capital in Vietnam, with Binh Tran of AVV.
- 10 years of venture capital in Vietnamwith Binh TranBinh Tran's mother did not celebrate when Klout sold. The news reached the press in 2014, and she called to ask if everything was okay and whether he still had a job. It closed six years of…