Vietnam megaprojects

Long Thanh International Airport: where it stands

Updated Live tracker. We keep this page up to date and change it as the project moves. See what changed.

Vietnam's largest airport, in Dong Nai about 40 km east of Ho Chi Minh City. Phase 1 is built for 25 million passengers a year.

A plane takes off at dawn from Tan Son Nhat airport, Ho Chi Minh City
Status
Under constructionFinal trials before commercial flights
Commercial opening
24 December 2026First stated 2025 in Jun 2015. VietnamPlus
Phase 1 completion
End of 2026First stated 2025 in Jun 2015. VnExpress International
International flights move from Tan Son Nhat
2027 winter scheduleFirst stated 2027 summer schedule in Nov 2025. Tuoi Tre News
Estimated cost
About US$16 billion for all phasesUnchanged since Jun 2015. Government news portal (baochinhphu.vn)

Where it stands

Key facts

Location
Long Thanh, Dong Nai, about 40 km east of Ho Chi Minh City Government news portal (baochinhphu.vn)
Phase 1 capacity
Terminal for 25 million passengers a year and a cargo terminal for 550,000 tonnes a year Tuoi Tre News
Full build
Three phases, up to 100 million passengers and 5 million tonnes of cargo a year Government news portal (baochinhphu.vn)
Investor
Airports Corporation of Vietnam (ACV), also named investor for phase 2 in January 2026 VnEconomy
Opening schedule
Up to 366 flights a week: 322 domestic and 44 international VietnamPlus
Road link
Ben Luc–Long Thanh expressway, 57.8 km, ends about 10 km from the airport VietnamPlus

Timeline

  1. Fifty staff went through the terminal as mock passengers, testing check-in, security, immigration and customs for domestic and international flights. VietnamPlus

  2. ACV told Dong Nai that commercial operations start at midnight on 24 December 2026. Target moved from 1 December 2026, the date in ACV's July plan, to 24 December 2026. VietnamPlus

  3. The Ben Luc–Long Thanh expressway, the road link from the Mekong Delta side, opened over its full length of nearly 58 km from 0:00 on 1 October. VietnamPlus

  4. ACV's plan sets 1 December 2026 as the commercial opening, with international flights moved from Tan Son Nhat in three phases up to the 2027 winter schedule. Tuoi Tre News

  5. After a site visit, the Prime Minister called for faster work so the airport can open for commercial flights in the fourth quarter of 2026. Government news portal (baochinhphu.vn)

Earlier
  1. The Ministry of Construction named ACV as investor for phase 2, which adds a second terminal for 25 million passengers a year and another runway. VnEconomy

  2. A Vietnam Airlines Boeing 787 from Hanoi made the first official landing, after a technical test flight on 15 December. Vietjet Air and Bamboo Airways also flew in for testing. Tuoi Tre News

  3. The plan set technical flights from December 2025 and commercial flights from June 2026. VnEconomy

  4. The National Assembly moved the phase 1 deadline from 2025 to the end of 2026 and added a second runway to phase 1 for about VND3.3 trillion. VnExpress International

  5. Construction of the airport broke ground. Tuoi Tre News

  6. The National Assembly approved the project at VND336.63 trillion, with phase 1 of one runway and one terminal for 25 million passengers a year, to start operating no later than 2025. National Assembly Resolution 94/2015/QH13 (LuatVietnam)

What comes next

  1. First commercial flights from midnight, after larger trial scenarios in the terminal24 December 2026 VietnamPlus

  2. Long-haul international flights and all cargo flights move from Tan Son Nhat to Long Thanh2027 summer schedule, from 28 March 2027 Tuoi Tre News

  3. ACV prepares the phase 2 feasibility study: a second terminal for 25 million passengers a year and another runway VnEconomy

  4. Ho Chi Minh City prepares the Thu Thiem–Long Thanh railway to link the city centre with the airport, with completion targeted for the end of 2030End of 2030 Vietnam Investment Review

See every project on the Vietnam megaprojects map

What it changes

Long Thanh adds a second big airport for Ho Chi Minh City and the south, next to Tan Son Nhat. Phase 1 is built for 25 million passengers a year, and ACV forecasts 8.76 million passengers in 2027 and more than 26.2 million by 2030. When all three phases are done, the airport can handle up to 100 million passengers and 5 million tonnes of cargo a year.

The airport sits about 40 km east of the city centre, so the road and rail links decide how long the trip takes. The 57.8 km Ben Luc–Long Thanh expressway, open in full since 1 October 2026, links the Mekong Delta with the airport area. The planned Thu Thiem–Long Thanh railway, about 47.7 km with 19 stations, is to be built in step with Metro Line 2 and connect Tan Son Nhat, the city centre and Long Thanh.

For Overseas Vietnamese flying home from Europe, the Americas, Oceania, Africa or the Middle East, the arrival airport changes: from the 2027 summer schedule, long-haul flights to the south land at Long Thanh instead of Tan Son Nhat. Flights within Northeast and Southeast Asia stay mainly at Tan Son Nhat until the 2027 winter schedule.

What does Overseas Vietnamese mean?

Get updates when this changes.

Changes to this page go out in the OV Vietnam Brief, with Vietnam’s big stories explained.