Long Thanh International Airport: where it stands
Vietnam's largest airport, in Dong Nai about 40 km east of Ho Chi Minh City. Phase 1 is built for 25 million passengers a year.

- Status
- Under constructionFinal trials before commercial flights
- Commercial opening
- 24 December 2026First stated
2025in Jun 2015. VietnamPlus - Phase 1 completion
- End of 2026First stated
2025in Jun 2015. VnExpress International - International flights move from Tan Son Nhat
- 2027 winter scheduleFirst stated
2027 summer schedulein Nov 2025. Tuoi Tre News - Estimated cost
- About US$16 billion for all phasesUnchanged since Jun 2015. Government news portal (baochinhphu.vn)
Where it stands
- Test flights are done: a Vietnam Airlines Boeing 787 made the first official landing on 19 December 2025, and staff ran full passenger trials in the terminal in November 2026.
- ACV plans up to 366 flights a week at the start, and long-haul international flights move over from Tan Son Nhat with the 2027 summer schedule.
- The Ben Luc–Long Thanh expressway opened in full on 1 October 2026, and a railway from Thu Thiem is targeted for the end of 2030.
Key facts
- Location
- Long Thanh, Dong Nai, about 40 km east of Ho Chi Minh City Government news portal (baochinhphu.vn)
- Phase 1 capacity
- Terminal for 25 million passengers a year and a cargo terminal for 550,000 tonnes a year Tuoi Tre News
- Full build
- Three phases, up to 100 million passengers and 5 million tonnes of cargo a year Government news portal (baochinhphu.vn)
- Investor
- Airports Corporation of Vietnam (ACV), also named investor for phase 2 in January 2026 VnEconomy
- Opening schedule
- Up to 366 flights a week: 322 domestic and 44 international VietnamPlus
- Road link
- Ben Luc–Long Thanh expressway, 57.8 km, ends about 10 km from the airport VietnamPlus
Timeline
Fifty staff went through the terminal as mock passengers, testing check-in, security, immigration and customs for domestic and international flights. VietnamPlus
ACV told Dong Nai that commercial operations start at midnight on 24 December 2026. Target moved from 1 December 2026, the date in ACV's July plan, to 24 December 2026. VietnamPlus
The Ben Luc–Long Thanh expressway, the road link from the Mekong Delta side, opened over its full length of nearly 58 km from 0:00 on 1 October. VietnamPlus
ACV's plan sets 1 December 2026 as the commercial opening, with international flights moved from Tan Son Nhat in three phases up to the 2027 winter schedule. Tuoi Tre News
After a site visit, the Prime Minister called for faster work so the airport can open for commercial flights in the fourth quarter of 2026. Government news portal (baochinhphu.vn)
Earlier
The Ministry of Construction named ACV as investor for phase 2, which adds a second terminal for 25 million passengers a year and another runway. VnEconomy
A Vietnam Airlines Boeing 787 from Hanoi made the first official landing, after a technical test flight on 15 December. Vietjet Air and Bamboo Airways also flew in for testing. Tuoi Tre News
The plan set technical flights from December 2025 and commercial flights from June 2026. VnEconomy
The National Assembly moved the phase 1 deadline from 2025 to the end of 2026 and added a second runway to phase 1 for about VND3.3 trillion. VnExpress International
Construction of the airport broke ground. Tuoi Tre News
The National Assembly approved the project at VND336.63 trillion, with phase 1 of one runway and one terminal for 25 million passengers a year, to start operating no later than 2025. National Assembly Resolution 94/2015/QH13 (LuatVietnam)
What comes next
First commercial flights from midnight, after larger trial scenarios in the terminal24 December 2026 VietnamPlus
Long-haul international flights and all cargo flights move from Tan Son Nhat to Long Thanh2027 summer schedule, from 28 March 2027 Tuoi Tre News
ACV prepares the phase 2 feasibility study: a second terminal for 25 million passengers a year and another runway VnEconomy
Ho Chi Minh City prepares the Thu Thiem–Long Thanh railway to link the city centre with the airport, with completion targeted for the end of 2030End of 2030 Vietnam Investment Review
What it changes
Long Thanh adds a second big airport for Ho Chi Minh City and the south, next to Tan Son Nhat. Phase 1 is built for 25 million passengers a year, and ACV forecasts 8.76 million passengers in 2027 and more than 26.2 million by 2030. When all three phases are done, the airport can handle up to 100 million passengers and 5 million tonnes of cargo a year.
The airport sits about 40 km east of the city centre, so the road and rail links decide how long the trip takes. The 57.8 km Ben Luc–Long Thanh expressway, open in full since 1 October 2026, links the Mekong Delta with the airport area. The planned Thu Thiem–Long Thanh railway, about 47.7 km with 19 stations, is to be built in step with Metro Line 2 and connect Tan Son Nhat, the city centre and Long Thanh.
For Overseas Vietnamese flying home from Europe, the Americas, Oceania, Africa or the Middle East, the arrival airport changes: from the 2027 summer schedule, long-haul flights to the south land at Long Thanh instead of Tan Son Nhat. Flights within Northeast and Southeast Asia stay mainly at Tan Son Nhat until the 2027 winter schedule.
More from Insights
All insights- Vietnam megaprojects: status, targets and timelinesThe big projects building Vietnam, from the North–South high-speed railway to Long Thanh airport and the metros. First and latest target dates, a source on every line, kept up to date.
- Venture capital in Vietnam, ten years inFrom $45 million in 2015 to $1.4 billion in 2021 and back to $509 million in 2025: ten years of venture capital in Vietnam, with Binh Tran of AVV.
- 10 years of venture capital in Vietnamwith Binh TranBinh Tran's mother did not celebrate when Klout sold. The news reached the press in 2014, and she called to ask if everything was okay and whether he still had a job. It closed six years of…